Menu

Moab Tailings Project Steering Committee Meeting

April 26, 2022 · Grand, UT
Source: Meeting minutes 2022-04-26 (PDF)
Retrieved April 25, 2026 from grandcountyutah.gov ↗
Confidence: 99%
High

Attendees

Mary McGann (Grand County Commission)
Judi Collins (Department of Workforce Services)
Joette Langianese (Grand County Representative)
Rani Derasary (City of Moab)
Tony Mancuso (Department of Natural Resources)
John Guenther (Grand County Planning and Zoning)
Dana van Horn (Grand Water & Sewer Service Agency)
Amy Tendick (National Park Service)
Melissa Stocks (Grand County Community and Economic Development)
Bill Jackson (Grand County Road Department)
Nicole Gaddis (Bureau of Land Management)
Philip Goble (Utah Department of Environmental Quality, Division of Waste Management and Radiation Control)
Russell McCallister (Federal Cleanup Director – Department of Energy)
Matt Udosovitch (Department of Energy)
Christopher Pulskamp (Project Engineer – Department of Energy)
Tom Bachtell (Pro2Serve, Project Senior Program Manager, Technical Assistance Contract)
Stephanie Lein (Pro2Serve, Environmental Scientist/Manager, Technical Assistance Contract)
Barbara Michel (Pro2Serve, Administrative Assistant, Technical Assistance Contract)
Liz Moran (Pro2Serve, Groundwater Manager, Technical Assistance Contract)
Mike Price (Public Citizen)
James Ritchey (Pro2Serve, Senior Program Manager, Technical Assistance Contract)
Jessica Thacker (Grand County UMTRA Liaison/Technical Inspector)
✓ Present: 22/22

Decisions

#Approval of minutes

PASSED Unanimous with one abstention

Agenda Items

#A

Call to order

The meeting was called to order at 3:01pm.

#C

Approve minutes

The committee approved the draft minutes for the January 25, 2022 Quarterly Meeting with minor corrections.

#D

Citizens to be heard

No comments were provided.

#E

Moab UMTRA project update

Russell McCallister provided an update on the project's progress.

#F

Update regarding status of remedial action contractor (RAC) contract and project funding

Russell McCallister provided an update on the RAC contract and project funding.

#G

Air monitoring and liaison activities status update

Jessica Thacker provided a detailed presentation on air monitoring data and activities.

#H

Update on lobbying efforts

Mary McGann provided an update on lobbying efforts for project funding.

#I

Stakeholders updates

Tony Mancuso provided a brief update on his field reduction team efforts.

#J

Future considerations

The committee discussed potential future uses of the project site.

#K

Adjournment

The meeting was adjourned at 3:48pm.

Public Comments

1 speaker
None · Topic: None

No public comments were provided.